how long does it take to renovate a bathroom

How long does it take to renovate a bathroom?

Table of Contents
    Add a header to begin generating the table of contents

    The process of calculating the amount of time necessary to renovate a bathroom can be frustrating and error-prone. And this is where estimation is more crucial than anywhere else, given that the majority of families consider it absolutely necessary to have their bathrooms operational as quickly as humanly possible. Leaving one of your bathrooms out of commision while the others are renovated is a significant inconvenience, unless you have the good fortune to possess multiple bathrooms.

    There is a good chance that by the time you make the decision to completely gut and renovate your bathroom, the idea of doing so has been percolating in your head for some time. You have the ability to picture your ideal bathroom as clearly as if it were already a reality.

    However, once the decision has been made to finally get started, it is critical to establish realistic expectations regarding the amount of time everything will require. In the event that you choose to handle everything in the traditional manner, by working with a general contractor, the process can be divided into a few stages, each of which requires careful consideration on your part.

    We have broken the phases that you should expect from a traditional project down into groups of tasks, which should provide you with a pretty good idea of what the process would look like if it were carried out. Unless you go with a solution that is more all-encompassing, each of the tasks that are described in this article is required to bring any project to life, although the specifics of those requirements may vary from project to project.

    Let's say you've decided to give your bathroom a makeover; in that case, congratulations! There is nothing more luxurious than taking a shower in a brand-new tub that is situated in a room that has been recently painted and features brand-new tiles. We couldn't be happier for you.

    However, if you're like the majority of homeowners, you're probably curious about the timetable for the project. How much time does it take to renovate a bathroom?

    It really depends on the specifics of the situation. After all, no two bathrooms are exactly the same. However, in order to give you an idea of what to anticipate, we have outlined a general timeline for you.

    How long does it typically take to renovate a bathroom? The typical amount of time needed to complete the construction of a bathroom will be somewhere between two and three weeks. In total, the planning, carrying out, and finishing touches on the renovation are estimated to take anywhere from two and a half months to three months to complete. Be prepared to submit an application for city permits and board approvals if you intend to move plumbing or electrical fixtures, as these are the factors that add the most delay to renovation schedules. Looking for bathroom renovators? Look no further. Hitch Property Constructions has you covered.

    Factors Affecting Remodel Time

    The truth is that it is extremely rare for a bathroom remodelling project to go exactly as planned, and a variety of factors can wreak havoc with your best efforts at scheduling, including the following:

    • Is the project going to be a superficial renovation or a rebuild from the ground up? The work could take as little as a few days or as much as many months, depending on the nature of the remodelling project that is being done.
    • Are you going to be the one doing the work, or are you going to hire a contractor? It has been the experience of more than one well-meaning homeowner that completing a home improvement project by performing all of the labour oneself and fitting in work time whenever it is available can take as much as a year to finish.
    • Is the contractor an owner-operator, or does he subcontract the work to other tradespeople like electricians, plumbers, and carpenters if you hire him to do the workout? Working with a remodeler who is also the owner and operator of the business may be the most cost-effective option; however, you should be aware that this type of remodeler will likely be juggling your project with several others while attempting to perform all of the work themselves. This indicates that a task that needs 10 or 15 actual workdays to complete could take anywhere from two to three months to finish.
    • Are all of the materials easily accessible, or do you need to place special orders for some of them, which could cause a delay in delivery? For example, if imported ceramic tile needs to be ordered, the completion of a project could be delayed by several weeks.
    • However, if you are working with a capable general contractor who is working with equally capable subcontractors, it is typically not too difficult to come up with an estimate of how long it will take to completely remodel a small bathroom, especially if you are working with a team that is equally competent.

    Under perfect conditions, the construction of a compact and fully functional bathroom can be finished in about 23 days on average. If there are no interruptions in the flow of work and it is assumed that no work is done on the weekends, this equates to approximately four and a half weeks, which is slightly longer than one month. In the real world, where there is always the possibility of downtime or unforeseen circumstances, the amount of time could be approximately doubled, coming in at 46 days, or approximately nine weeks.

    Renovate A Bathroom 1

    Prepare for the Unexpected

    The following schedule makes the following assumptions: that the work is being carried out by an experienced general contractor who is collaborating with qualified subcontractors; that all tradesmen arrive at the scheduled time; that no one gets sick; that materials are readily available; and that you, the homeowner, do not issue any change orders that slow down the progress.

    Most importantly, this is a hypothetical version of the schedule. In other words, dead days have been eliminated, and the timing of all workdays has been rearranged to ensure that there are no gaps in the schedule. It presupposes that as soon as one worker finishes their shift, the next one steps in immediately to take their place. Again, you should not be surprised if the actual schedule is approximately twice as long as this idealised one.

    Pre Construction Phase

    UNDERSTANDING THE PROJECT ( 1 – 4 weeks ) 

    In order to find a contractor who is a good fit with what it is that you are trying to accomplish with the renovation, it is essential to have a clear understanding of what it is that you hope to accomplish with the project. When you go into the discussion and planning process of your renovation with a solid plan on layout as well as a general vibe of materials and products, it will make the process much more efficient overall.

    Find the Right Renovation Company ( 1 – 4 weeks ) 

    It is of the utmost importance to do some research and locate a company that embodies both your personality and your sense of style. There are numerous remodelling companies that focus on a particular style or ambience; therefore, it is important to find one that is compatible with your preferences. Do you want a complete overhaul or just some changes made here and there? It is essential to keep this in mind because some businesses do not provide services for partial renovations.

    Sign Contracts and Finalise construction Schedules. ( 1 week ) 

    Before beginning construction, the chosen contractor will have a contract drawn up for you to sign before beginning work. Once you have selected the contractor who is the best fit for you, the contractor will have the contract drawn up. Information pertaining to the work that needs to be done, an estimated timeline for completion, and the timing of payments at various points throughout the project will all be included in the contract. Be sure to give this contract a careful read through and keep an eye out for any small print that may contain important information you need to know.

    Obtain Permits and Approvals (Ranges widely depending on which approvals you need for this project, be prepared and allow for weeks – months) 

    The process of obtaining the necessary permits and approvals is likely to be the one and only point at which difficulties may arise. In order to get approval from the board, any renovations you make to an apartment room or other spaces that aren't houses on their own are required. Just this step can take a couple of months!

    Source Materials (Wide range, prepare in advance for weeks) 

    If you are in charge of locating all of the necessary materials, then you need to make sure that you place your orders as soon as the design plan is finished being drafted. Going shopping for components that you want to instal in your bathroom can be a very fun and interesting experience to have. Having said that, it won't be fun to have to delay the construction time because one of your features (such as a toilet, bath, or shower) wasn't delivered on time.

    Design – 1 to 4 weeks

    It is necessary to complete some preliminary work in your bathroom in order for any renovations to be carried out there. Before you meet with your contractor to discuss your remodelling project, you should have a good idea of what you want the end result to be. You will be required to go over your plans with a contractor, who will require some time to take space measurements, learn about the features that you want to incorporate, and collaborate with you to determine the optimal location for those features. These particulars will also assist your contractor in developing an estimate of the total cost that will be incurred by you.

    Ordering Materials – 1 to 8 weeks

    After the design has been finalised and a price has been agreed upon, either you or your contractor can start placing orders for the necessary materials. However, there are some things that should be kept in mind. This stage can take a lot more time if, for example, you order bespoke cabinets or tiles that have to be shipped from another country. This can also result in certain materials arriving in a very staggered fashion, especially if there are a lot of them. Collaborate with both your contractor and your suppliers to devise a timetable that features the minimum number of gaps possible.

    Are you interested in remodelling your bathroom? No need to look any further. You have nothing to worry about when you hire Hitch Property Constructions.

    Construction – 2 to 5 weeks

    The first step in the renovation process is demolishing the previous occupants of the bathroom space. This step is pretty straightforward; it takes the most of two days and includes things like preparing the site, protecting the floor (unless you're also redoing that), and installing dust barriers to contain the work and protect the rest of the house. (Days 1-2)

    After the previous bathroom has been gutted, the new bathroom's layout, framing, and backing can be constructed. This step brings the design blueprints to life in the form of the finished bathroom. The roughing in of the plumbing and electrical systems will take place over the next few days, followed by the installation of the tub or shower, as well as the installation of new exhaust fans and ventilation. (Days 3-4)

    After the essential components of the bathroom have been installed, the drywall can be hung in the appropriate places. The installation of boards that are resistant to moisture will also be a part of this process. These boards will be placed in sensitive areas such as those around the bathtub or shower. (Days 5-10)

    The placement of tiles is made possible after the walls have been put up. This procedure can take approximately one week, give or take a few days, on average. When extensive drywall work is required, when the temperature in the room does not allow mud to dry quickly, or when the ceilings are also being changed from a textured to a smooth profile, it is possible for it to last a little bit longer. (Days 11-14)

    After the drywall has been mounted, the wall and floor tiles can be laid, the grout can be applied, and the tiles can be sealed. On average, this procedure will take between four and five days to complete. Following the installation of the tiles, the walls of the bathroom can be primed and painted with the first coat of paint. (Days 15-20)

    Then, the finishing touches of the construction are added. Following the installation of the vanity, the counter, as well as the plumbing and electrical fixtures, additional coats of paint are applied, and finishing touches such as towel racks are mounted. (Days 21-23)

    After the construction has been effectively finished, there are still a few steps that need to be taken to ensure that the space is ready to be used. These steps are relatively minor, but they are nonetheless essential. To ensure that the room can be used without any complications, the contractor will need to thoroughly clean the area and conduct inspections of the electrical and plumbing systems. (Days 24-25)

    After you have completed all of these steps, you will finally be able to take advantage of your newly renovated bathroom.

    Preparing for your bathroom renovation: the 5 phases

    You need to be familiar with the process of a renovation from beginning to end in order to have an accurate estimate of how long your project might take. We have determined that there are five distinct stages, and based on the presumption that there will be no hiccups, we have provided an estimated timeline of how long each phase takes.

    The following constitutes each of the five phases:

    • The activities of planning and development
    • Taking apart your outdated bathroom.
    • The preliminary work on the brand-new bathroom.
    • Adjusting to your brand-new features.
    • The final details and adjustments

    Phase 1: Planning and development

    The phase that consists of planning and development takes the lion's share of the time. It includes the time spent conducting research on the bathroom design that you want, determining the cost of your bathroom renovation, hiring a renovation company, and creating a blueprint for you and your tradespeople to work from.

    It is possible that you will need to submit an application for planning permission depending on the scale of your project. This is also the time to place your order for your fixtures and fittings, to ensure that all of the components arrive in plenty of time before the start date of the onsite work.

    The time frame that has been estimated ranges from one month to six months.

    Phase 2: Stripping your old bathroom

    The process of removing all of the fittings and fixtures from your existing bathroom may take a couple of days. However, this could change depending on a number of factors, including whether the bathroom is on the first or second floor, whether you plan to keep any of the existing fittings, and whether the walls will require any structural alterations.

    Time required is estimated to be one or two days.

    Phase 3: Groundwork for new bathroom

    It is much simpler for the plumber and the electrician to come in and do a rough-in fit when there is nothing but a blank canvas. This indicates that they instal all of the wiring and plumbing, but they do not connect any of it while the construction work is still in progress. Carpenters, plasterers, and tilers are the next tradespeople to arrive. They work on surfaces that need to be prepared for tiling, as well as walls that need to be rendered and constructed.

    Timeframe estimates range from two to five days.

    Phase 4: Fitting your new features

    The fourth phase, in which you will finally see your new bathroom design come to life, is likely to be the most exciting of all the phases. It's the time when all of your new fixtures are put in, so there will be a lot of work for you to do.

    Priority will be given to finishing the essential tasks first, including tiling, painting, grouting on the walls or floor, and waterproofing. Due to the fact that some of these tasks require drying time, there may be periods of inactivity during this phase of the process. After ensuring that everything is in its proper location, the plumber will finish making the necessary connections for your shower, bathtub, toilet, and basins. In addition, your electrician will reattach the electrical connections for the lights, towel rails, extractor fans, and floor heating.

    Glass fixtures, such as shower doors and mirrors, are installed very late in the process, reducing the likelihood that they will break or become damaged as a result of the ongoing work.

    The time frame is estimated to be anywhere from five to ten days.

    Phase 5: The finishing touches

    Following the completion of the installation of everything and the allowing of sufficient time for it to dry, we will perform a final inspection and clean. After that has been taken care of, the bathroom is entirely yours to use however you like.

    Time required: approximately one third of a day

    Hitch Property Constructions has the best range of renovations services to help you create your dream house.

    How Long Does it Take to Remodel a Small Bathroom?

    The length of the timeline is determined by a variety of different aspects of the situation. One of the important factors to consider is the size of the bathroom. After all, renovating a smaller room requires significantly less labour and, as a result, a shorter amount of time.

    In spite of this, there are a few chores that always take the same amount of time, regardless of how large the bathroom is. Even if your bathroom renovation is a relatively straightforward project, for instance, the rough-in phase could take more than a week to complete. This is due to the fact that our schedule is reliant on the accessibility of plumbers and electricians to complete their work. Because we are unable to finish building the walls until the wiring and plumbing issues are resolved, we will have to wait for those issues to be resolved.

    Additional Factors that Increase the Timeline

    Every schedule for a bathroom remodel gets our best effort in terms of planning, from the very beginning to the very end. However, we cannot guarantee that this timetable will not be altered in any way.

    During the course of the renovation, we are frequently sidetracked by unforeseen events. In the event that any of these unforeseen events occur, completing the task might require some additional time.

    For instance, it is essential to keep in mind that the total amount of time required to complete the project will increase if any changes are made. It is necessary for us to submit a change order prior to moving forwards with the project if the client decides to change their mind in the middle of the process.

    Any change, regardless of how insignificant it might appear to be, is subject to a change order. To put it another way, the addition of something as substantial as a new wall or as insignificant as a change in paint colour can both add additional days to our schedule. Therefore, if you want us to leave your home in the shortest amount of time possible, you need to make sure that you have already decided what you want to do before we get started.

    Beware of Complications

    Keep in mind that the renovation schedule can be disrupted by a number of different factors. It is possible that unexpected problems, such as rot or mould, will be discovered during demolition; products may arrive damaged and need to be replaced; special-order items may take longer to arrive (hence the possibility of waiting up to eight weeks for materials); and particular contractors, such as plumbers or carpenters, may have scheduling conflicts, which can delay work on your project.

    You can use this outline to get a general idea of how long it will take to complete the various components of a renovation. If your bathroom is on the smaller side, you can probably expect the project to be completed in less time. It will be easier for the project to remain on track and be completed on time if timeline expectations are established in advance. Check out our extensive range of home designs at Hitch Constructions.

    FAQs About Bathroom Renovation

    The answer to this question is highly dependent on the scope of the project at hand; it can take anywhere from three to four weeks to remodel a bathroom. The completion of larger remodelling projects can take anywhere from four to six weeks, but in general, you should be prepared for the majority of remodelling projects to take at least one month.

    Expect it to take between one and two days if you are the only customer. When you move plumbing fixtures like the toilet, tub/shower, or sink, or when you change the layout of the electrical system, the roughing-in phase of the project takes longer.

    When compared to the time necessary to repair other types of floors, such as tile or engineered wood, a straightforward vinyl floor can be installed in just one morning. The flooring installation process can take up to two days on average to complete.

    After the sheets have been hung, the waterproofer will come in and finish waterproofing the room as per the specifications. This ensures that there will be no leaking showers in the years to come and a tight water seal! It takes at least twenty-four hours for waterproofing to dry completely, and the process can take at least two days if there are two or three coats.

    Given that the typical lifespan of a bathroom is somewhere around ten years, the design of your bathroom should follow this long-lived rule without exception.

    Scroll to Top