Bathroom remodel time estimates are notoriously difficult to get right. Given that the vast majority of households view having working restrooms as an absolute necessity, this is perhaps the single most important area where estimation is critical. If you don’t have the good fortune to own numerous bathrooms, having one out of commision while the others are repaired is a major nuisance.
The thought of tearing out the old and installing the new in your bathroom may have been floating about in your thoughts for a while before you finally decided to go ahead and do it. You may envision your perfect toilet as clearly as if it actually existed.
When the time comes to really get started, though, it’s important to set reasonable goals for how long things will take. If you want to hire a general contractor and do everything the old-fashioned way, there are several steps you’ll need to take into consideration.
For a more concrete picture of how a typical project is carried out, we have segmented the stages into groups of work. All of the steps outlined in this article are necessary to bring a project to life, although the specifics may vary depending on the nature of the project. This is true even if you choose a more comprehensive solution.
You’ve decided to remodel your bathroom, which is fantastic! There is nothing more indulgent than a refreshing shower in a freshly tiled and painted bathroom with a brand-new tub. We’re so happy for you, it hurts.
However, if you’re like most homeowners, you’re probably wondering how long the project will take. Just how long does it typically take to completely remodel a bathroom?
It is highly conditional on the particulars of the circumstance at hand. Since there is some degree of individuality between each bathroom, no two should be treated the same. However, we have provided a rough schedule to give you an idea of what to expect.
Bathroom remodel time: how long does it usually take? Bathroom renovations typically take between two and three weeks to complete. It is anticipated that the makeover will take between two and a half and three months to complete, including the planning stage, construction, and final touches. Plan ahead to apply for city permits and board permissions if you want to relocate plumbing or electrical fixtures; these are the main causes of remodelling delays. Looking for bathroom renovators? Look no further. Hitch Property Constructions has you covered.
Factors Affecting Remodel Time
It’s true that bathroom renovations almost never go according to schedule, and that several factors, such as those listed below, might throw a wrench in your plans:
- What kind of remodelling do you have in mind for this project, if any at all? Depending on the complexity of the renovation, the process could take just a few days or several months to complete.
- Undertake you plan to do the task yourself, or employ a third party? Many well-intentioned homeowners have discovered the hard way that it might take as long as a year to undertake a home renovation project if the homeowner is doing all of the work themselves and only working when they have free time.
- If you hire a contractor to do the workout, will he do it alone, or will he outsource the job to others, such as electricians, plumbers, and carpenters? The most cost-effective choice may be to hire a remodeler who is also the business owner and operator; however, you should be aware that this remodeler will likely be juggling your job with several others while attempting to accomplish all of the work themselves. It could take two to three months to perform a task that normally takes ten to fifteen working days.
- Is it possible to get your hands on all the required components without resorting to time-consuming special orders? Project completion could be delayed by a few weeks, for instance, if imported ceramic tile needs to be ordered.
- When working with a skilled general contractor and subcontractors, however, it is usually not too difficult to predict how long it will take to rebuild a tiny bathroom from top to bottom.
In ideal conditions, it takes only around 23 days to complete the building of a small, high-quality toilet. It would take about four and a half weeks, or little longer than a month, if there were no disruptions in the flow of work and no work was done on the weekends. The time could be about quadrupled to 46 days (or about nine weeks) in the actual world due to the presence of downtime and unforeseen occurrences.
Prepare For The Unexpected
The following timeline assumes the following: the work is being done by a seasoned general contractor with the help of competent subcontractors; all tradesmen arrive at their appointed times; no one gets sick; all necessary supplies are on hand; and you, the homeowner, do not request any time-consuming changes.
First and foremost, keep in mind that this is just a made-up timetable. In other words, the schedule now has no blank spots because dead days have been removed and the order of all workdays has been shifted. It assumes that when one employee’s shift ends, another one instantly begins working in their place. Once again, it is reasonable to expect that the actual schedule will be roughly twice as long as this hypothetical one.
Pre Construction Phase
Understanding The Project ( 1 – 4 Weeks )
In order to select a contractor that is a good fit with what you are attempting to accomplish with the makeover, you must first have a clear knowledge of those goals. It is considerably more productive to enter the conversation and planning phase of your remodelling with a strong strategy on layout and a general mood of materials and goods in mind.
Choose The Best Renovation Company ( 1 – 4 Weeks )
It’s important that you put in the time and effort required to find a firm whose values and aesthetics align with your own. It is essential to pick a remodelling firm that shares your aesthetic interests, as there are many out there. Is it a major revamp you’re after, or can we get away with a few tweaks here and there? Some companies do not offer their services for partial renovations, so keep this in mind.
Contracts Should Be Signed And Construction Schedules Should Be Finalized. ( 1 Week )
The selected builder will have a contract ready for you to sign before any building begins. When you’ve decided on the right contractor, he or she will draught the contract. The contract will detail the tasks to be performed, the duration of time expected to complete them, and the schedule for payments at various stages of the project. Please read this document thoroughly, paying special attention to any fine print that may contain crucial information.
Get Permits And Approval (Be Prepared And Allow For Weeks – Months Depending On Which Approvals You Need For This Project)
Problems are more likely to develop during the time spent applying for and receiving the required permissions and approvals. Any changes you make to a room in an apartment building or any other building that isn’t a single-family home will need board approval. This procedure alone may take a few months!
Source Materials (Wide Range, Prepare Weeks In Advance)
If you’re in charge of sourcing all the materials, don’t wait until the design plan is complete before placing your orders. It may be a lot of fun and exciting to shop for the fixtures and fittings you want to put in your bathroom. On the other hand, you don’t want to have to push back the schedule because anything you ordered (such a sink, bathtub, or shower) wasn’t available when you needed it.
Design – 1 To 4 Weeks
There is prep work that needs to be done in your bathroom before any renovations can begin there. You should have a clear vision in mind for your remodel’s final product before meeting with your contractor to discuss the details of the job. A contractor will want to meet with you to go through your designs in detail, at which time he or she will measure the available area, research the features you wish to have installed, and work with you to decide the best placement for those components. Your contractor can better estimate the full cost to you with this information in hand.
Ordering Materials – 1 To 8 Weeks
After the plan is finalised and the cost is settled upon, you or your contractor can begin ordering the required supplies. Nonetheless, there are considerations to take into account. Additional time may be needed at this point if, for instance, you are having custom cabinets made or tiles imported from another nation. If there are a lot of supplies, this can also cause their arrival to be spread out over a long period of time. It is important to work with your contractor and suppliers to create a schedule with as few lulls as feasible.
Construction – 2 To 5 Weeks
The first stage in the restoration is to tear down the existing lavatory. Preparing the spot, covering the floor (unless you’re also renovating it), and setting up dust barriers to contain the job and protect the rest of the house can all be accomplished in no more than two days. (Days 1-2)
A new bathroom’s design, framing, and backing can be built after the old one has been gutted. In this phase, the bathroom takes shape according to the architect’s plans. Over the next two days, we’ll be roughing in the plumbing and electricity, then installing the tub or shower and new exhaust fans and ventilation. (Days 3-4)
Drywall can be hung once all the necessary fixtures and fittings for the bathroom have been installed. A component of this procedure will also involve the installation of water-proof boards. Boards like these will be used in bathrooms to prevent accidents in wet regions. (Days 5-10)
After the walls are up, you may start laying the tiles. In general, this process takes around a week. It can be made to last a little longer when there is a lot of drywall work to be done, the temperature in the space is not conducive to mud drying rapidly, or the ceilings are also being converted from a textured to a smooth profile. (Days 11-14)
Once the drywall is up, the flooring and walls can be tiled, grouted, and sealed. This process typically takes four to five days to finish. It’s time to prime and paint the bathroom walls once you’ve put up the tiles. (Days 15-20)
The final steps in building are then taken. After the vanity, counter, plumbing, and electrical fixtures are all set up, the last touches like towel racks can be installed and more paint can be done. (Days 21-23)
There are last measures that must be completed once construction is essentially complete before the area may be utilised. These aren’t major tasks, but they need to be done. The contractor must perform extensive cleaning and inspections of the room’s electrical and plumbing systems before it can be used. (Days 24-25)
Once you’ve done everything on this list, your bathroom remodel will be complete, and you can start enjoying it.
The 5 Phases Of Preparing For A Bathroom Renovation
A realistic time frame for your restoration project can’t be estimated without first having a thorough understanding of the entire process. We’ve narrowed the process down to five stages, and we’ve included an anticipated timeframe for how long each one should take if nothing goes wrong.
These are the components of each of the five stages:
- Planning and development activities
- Dismantling your old bathroom.
- The groundwork for the brand-new bathroom.
- Getting used to your new features.
- Final tweaks and details
Phase 1: Planning And Development
The bulk of the time is spent on the development and planning stage. It involves everything from finding a business to do the renovation for you to producing a blueprint so that you and the workers know exactly what has to be done and how much time and money you have to spend.
Depending on the scope of your project, you may need to seek necessary planning approvals. Also, now is the time to order any necessary fixtures and fittings to ensure they will arrive well in advance of the scheduled onsite construction start date.
Predicted duration is between one to six months.
Phase 2: Getting Rid Of Your Old Bathroom
It may take a few days to completely gut your current bathroom of all of its fixtures and equipment. A number of variables, such as whether the bathroom is on the first or second story, if you intend to reuse any of the old fixtures, and whether structural alterations are needed to the walls, could influence this estimate.
It’s anticipated that one or two days will be needed.
Phase 3: Groundwork For New Bathroom
When there is nothing there but a blank slate, the plumber and electrician can come in and conduct a rough-in fit with much more ease. The wiring and plumbing are installed, but not connected, until the building is complete. Following the arrival of the bricklayers and plumbers will be the carpenters, plasterers, and tile setters. They do work such as rendering walls and constructing surfaces in preparation for tiling.
Estimates of the duration range from two to five days.
Phase 4: Fitting Your New Features
You should expect the most excitement during the fourth and final phase, when your new bathroom design is brought to life. There will be a lot to accomplish as this is the time when your new fixtures are being installed.
Tiling, painting, grouting on walls or floors, and waterproofing will be prioritised over less important activities. This stage of the procedure may feature periods of inactivity due to the need for some jobs to dry. When the plumber is satisfied that everything is where it should be, he or she will complete the plumbing connections for your new shower, toilet, bathtub, and sinks. In addition, after he is finished, the electrician will reattach the wiring for your lights, extractor fans, towel rails, and floor heating.
When it comes to installing glass fixtures like shower doors and mirrors, it’s best to wait until the very end to reduce the risk that they will be broken or damaged during the construction process.
It could take as little as five days or as long as ten days.
Phase 5: The Finishing Touches
After everything has been installed and given enough time to dry, we will do a final check and clean. Once that’s out of the way, you’re free to do as you like there.
Time required: roughly one-third of a day.
Hitch Property Constructions has the best range of renovations services to help you create your dream house.
How Long Does A Small Bathroom Renovation Take?
Timelines vary in duration depending on a number of factors. Bathroom space is a crucial consideration. After all, a smaller room requires much less time and effort to remodel because of the reduced quantity of work involved.
Regardless of the size of the bathroom, there are a few tasks that always require the same amount of time. Your bathroom remodel, for example, may seem simple on the surface, but the rough-in step alone could take more than a week. This is because our timetable is dependent on the availability of tradespeople like plumbers and electricians to carry out their tasks. We will have to wait for the electricity and plumbing problems to be fixed before we can complete building the walls.
Additional Factors Extending The Timeline
From the very first to the very last step of the process, we put out our finest planning effort into every bathroom renovation timetable. We are unable to promise, however, that this schedule will not be adjusted in any manner.
Numerous unanticipated complications have arisen during the course of the refurbishment. If any of these unanticipated problems crop up, it may take a little longer to finish the job.
For example, it’s crucial to remember that making adjustments will extend the overall time needed to finish the project. If the client wishes to make a modification midway through the project, we will need to file a change order to get their approval before continuing.
A change order must be submitted for any modification, no matter how little it may seem. Whether it’s the construction of a new wall or the selection of a new paint colour, we may need to allocate extra time in our calendar. Make sure you know exactly what you want before we arrive so that we can get out of your house as soon as possible.
Beware Of Complications
Do not forget that a variety of things can cause delays in the renovation timetable Problems like rot and mould may not become apparent until demolition begins, supplies may arrive broken, and need to be replaced, special-order items may take longer to arrive (which means you may have to wait up to eight weeks for materials), Moreover, certain contractors, such as plumbers or carpenters, may be unavailable due to prior commitments, thereby delaying the completion of your project.
This plan will give you a rough estimate of how long it will take to finish the various parts of a remodel. With a smaller bathroom, you may generally anticipate a shorter duration for the renovation. Setting realistic deadlines in advance can help ensure the project stays on track and is finished on time. Check out our extensive range of home designs at Hitch Constructions.
Conclusion
Bathroom remodelling estimates need to be more accurate. If you don’t have numerous bathrooms, not having one is terrible. Bathroom renovations usually take two weeks. A small bathroom renovation takes how long? A 10-to-15-day job could take three months.
The most cost-effective remodeler may be the firm owner. It would be best if you could find a company that shares your values. Finding a remodelling business that shares your aesthetics is vital. Not all companies offer half-remodelling services. Before meeting with your contractor, you should know what you want from your makeover.
Custom cabinetry or imported tiles can add weeks to the timeframe. Many supply drops could last a long time. After drywall, add tiles, grout, and sealant. This process takes four to five days. Install towel racks and finish painting now.
The plumber and electrician will install the pipes and fittings for your new sinks, shower, and toilet. Priorities include waterproofing, tiling, painting, and grout floors and walls. Please list your needs before we arrive at your home. Setting realistic deadlines in advance helps keep projects on track and schedule.
Content Summary
- Bathroom remodelling time estimates are notoriously difficult to get right.
- When the time comes to get started, it’s important to set reasonable goals for how long things will take.
- If you want to hire a general contractor and do everything the old-fashioned way, there are several steps you’ll need to take into consideration.
- For a more concrete picture of how a typical project is carried out, we have segmented the stages into work groups.
- All of the steps outlined in this article are necessary to bring a project to life, although the specifics may vary depending on the nature of the project.
- You’ve decided to remodel your bathroom, which is fantastic!
- However, we have provided a rough schedule to give you an idea of what to expect.
- Bathroom renovations typically take between two and three weeks to complete.
- Depending on the complexity of the renovation, the process could take just a few days or several months to complete.
- Many well-intentioned homeowners have discovered that it might take as long as a year to undertake a home renovation project if the homeowner is doing all the work themselves and only working when they have free time.
- The most cost-effective choice may be to hire a remodeler who is also the business owner and operator; however, you should be aware that this remodeler will likely be juggling your job with several others while attempting to accomplish all of the work themselves.
- However, when working with a skilled general contractor and subcontractors, it is usually not too difficult to predict how long it will take to rebuild a tiny bathroom from top to bottom.
- In ideal conditions, it takes only around 23 days to complete the building of a small, high-quality toilet.
- To select a contractor that is a good fit with what you are attempting to accomplish with the makeover, you must first have a clear knowledge of those goals.
- It is considerably more productive to enter the conversation and planning phase of your remodelling with a strong strategy on layout and a general mood of materials and goods in mind.
- You must put in the time and effort required to find a firm whose values and aesthetics align with yours.
- It is essential to pick a remodelling firm that shares your aesthetic interests, as many are out there.
- The selected builder will have a contract ready for you to sign before the building begins.
- When you’ve decided on the right contractor, he or she will draft the contract.
- If you’re in charge of sourcing all the materials, don’t wait until the design plan is complete before placing your orders.
- Shopping for the fixtures and fittings you want to put in your bathroom may be a lot of fun and exciting.
- Prep work needs to be done in your bathroom before renovations can begin there.
- You should have a clear vision in mind for your remodel’s final product before meeting with your contractor to discuss the details of the job.
- Your contractor can better estimate the full cost to you with this information in hand.
- After the plan is finalised and the cost is settled, you or your contractor can begin ordering the required supplies.
- Working with your contractor and suppliers is important to create a schedule with as few lulls as feasible.
- In this phase, the bathroom takes shape according to the architect’s plans.
- Days 3-4) Drywall can be hung once all the necessary fixtures and fittings for the bathroom have been installed.
- A component of this procedure will also involve the installation of water-proof boards.
- Days 11-14) Once the drywall is up, the flooring and walls can be tiled, grouted, and sealed.
- It’s time to prime and paint the bathroom walls once you’ve put up the tiles.
- Days 24-25) Once you’ve done everything on this list, your bathroom will be complete, and you can start enjoying it.
- A realistic time frame for your restoration project can’t be estimated without thoroughly understanding the entire process.
- These are the components of each of the five stages: Planning and development activities, Dismantling your old bathroom.
- Depending on the scope of your project, you may need to seek necessary planning approvals.
- Some variables, such as whether the bathroom is on the first or second story if you intend to reuse any of the old fixtures, and whether structural alterations are needed to the walls, could influence this estimate.
- The wiring and plumbing are installed but not connected until the building is complete.
- When your new bathroom design is brought to life, you should expect the most excitement during the fourth and final phase.
- There will be a lot to accomplish as this is when your new fixtures are installed.
- This stage of the procedure may feature periods of inactivity due to the need for some jobs to dry.
- When the plumber is satisfied that everything is where it should be, they will complete the plumbing connections for your new shower, toilet, bathtub, and sinks.
- After everything has been installed and given enough time to dry, we will do a final check and clean.
- Time required: roughly one-third of a day. Timelines vary in duration depending on some factors.
- Your bathroom remodel, for example, may seem simple on the surface, but the rough-in step alone could take more than a week.
- We will have to wait for the electricity and plumbing problems to be fixed before we can complete building the walls.
- Numerous unanticipated complications have arisen during the refurbishment.
- If these unanticipated problems crop up, finishing the job may take a little longer.
- Make sure you know exactly what you want before we arrive so we can get out of your house as soon as possible.
- This plan will give you a rough estimate of how long it will take to finish the various parts of a remodel.
- With a smaller bathroom, you may generally anticipate a shorter duration for the renovation.
- Setting realistic deadlines in advance can help ensure the project stays on track and is finished on time.
FAQs About Bathroom Renovation
How Long Does It Take for a Bathroom to Be Redone?
The answer to this question is highly dependent on the scope of the project at hand; it can take anywhere from three to four weeks to remodel a bathroom. The completion of larger remodelling projects can take anywhere from four to six weeks, but in general, you should be prepared for the majority of remodelling projects to take at least one month.
Can You Remodel a Bathroom in 2 Days?
Expect it to take between one and two days if you are the only customer. When you move plumbing fixtures like the toilet, tub/shower, or sink, or when you change the layout of the electrical system, the roughing-in phase of the project takes longer.
How Long Does It Take To Replace a Small Bathroom Floor?
When compared to the time necessary to repair other types of floors, such as tile or engineered wood, a straightforward vinyl floor can be installed in just one morning. The flooring installation process can take up to two days on average to complete.
How Long Does It Take To Waterproof and Tile a Bathroom?
After the sheets have been hung, the waterproofer will come in and finish waterproofing the room as per the specifications. This ensures that there will be no leaking showers in the years to come and a tight water seal! It takes at least twenty-four hours for waterproofing to dry completely, and the process can take at least two days if there are two or three coats.
How Long Should a Bathroom Last?
Given that the typical lifespan of a bathroom is somewhere around ten years, the design of your bathroom should follow this long-lived rule without exception.